Ewing Creek – Brick Church Equalization Facility
About This Project
2-phase project: first phase consisted of blasting and unclassified excavation for a 10.6 million gallon tank and pump station. Second phase – after tank was built – consisted of installation of storm water drainage, bioretention basin and final restoration.
Date
October 2017 to January 2019
Project Details
Clients
Metro Government of Nashville and Davidson County
Project Type
Sewer Pipeline