Hilton Brentwood

About This Project

WBG’S pipe rehab team rehabilitated 58 LF of 18"CMP utilizing PVC fold & form technology at the Hilton Brentwood/Nashville Suites. This storm drain was located underneath the hotel entrance, and a trenchless approach reinforced the storm drain for years to come without disrupting hotel operations and guest flow or negatively impacting landscaping and other aspects of the existing campus.  

Project Details

CLIENT

Hilton Hotels & Resorts

Project Type

Pipe Rehabilitation – PVC Fold & Form


Pipe RehabKristi Simard